3-5. Lesson 3 Practice Exercise
__________________________________________________________________
The following items will test your knowledge of the material covered in this
Instructions
lesson. There is only one correct or best answer for each item. When you
complete the exercise, check your answers with the answer key that follows. If
you answer any item incorrectly, study again that part of the lesson which
contains the portion involved.
__________________________________________________________________
1.
Which of the following publications will provide the best information to determine an
installation's capacity to accept cargo?
A.
Available Labor Report.
B.
Facilities and Services Guide.
C.
Facility Financial Summary Report.
D.
Facilities Capacity Report.
2.
Which of the following would not be included in the Installation Capacity Report?
A.
Maps of the installation.
B.
C.
Storage areas.
D.
Number and type of railcars available for use.
3.
When determining an installations limitations which of the following will determine its reception
capability weakness?
A.
Total railcar capacity.
B.
Roadnet within the installation.
C.
Team tracks.
D.
All of the above.
4.
Which of the following uses DISRs to monitor the spotting, loading, pulling of transport assets,
and the delivery of cargo?
A.
TAMCA.
B.
MCT.
C.
MCC.
D.
MHE.
__________________________________________________________________
Continued on next page
3-13
TR2013