5-9. Lesson 5 Practice Exercise Answer Key and Feedback
Item
Correct Answer and Feedback
1.
C.
TM3. Page 5-4.
2.
A.
TMT. Page 5-8.
3.
D.
TMC. Page 5-6.
4.
A.
TML. Page 5-6.
5.
B.
TMS. Page 5-7.
6.
B. False.
Occasionally it is necessary to hold shipments. A case in point
might be when complete diversion data to include the new
consignee and fund citation are not available. However, not all
shipment situations justify a shipment being held for a new
consignee. Page 5-2.
7.
D.
Transportation officers assigned to a POE/POD Movement Control
Center (MCC) must ensure that at least one of the following
conditions occurs before an activity requests a shipment hold
authorization:
A supply cancellation.
Termination of a project.
Modification of Permanent Change of Station (PCS) orders
regarding personal property shipments.
Termination of logistics buildup.
Page 5-3.
TR1025