Four methods of train operation aid in overcoming the
difficulties encountered immediately upon entry into a theater.
Careful plans should be made in determining the proper method for
early railway operations; any one or a combination of methods may be
used. The four methods of train operation are fleet, manual block,
train order, and timetable. They are discussed in that order in the
four main paragraphs that follow; important points about the four
methods are summarized in table II which follows paragraph 3.8.
During the early stages of theater development, before
rehabilitated or constructed, the fleet operation is used. The
primary advantage of this method is its simplicity. Loaded trains
move forward for specific periods, normally 4, 8, 12, or 24 hours.
At the end of the designated period, empty trains return toward rear
areas for a corresponding period.
Figure 3.1 shows a railway
as it might appear in an
undeveloped theater. Imagine
that the forward area of the
combat zone is just forward of
railhead A, and the remainder of
the railway north of it is in
enemy hands. The theater has
not yet expanded far enough to
and the sidings at stations X
and Y are not usable. A single
track railway runs from the port
terminal to the railhead.
Locomotives and railway cars are
ready to begin fleet operation.
Railhead A can accommodate four
trains at one time.
Four trains are sent out at
1hour intervals from the port
terminal to the railhead.
It takes 10 hours running
Figure 3.1. Railway
Net
in
time for each train and 10
Unexpanded Theater.
hours to unload each train
at the railhead. Therefore,