6 RECOMMENDATIONS AND COST
ESTIMATES FOR REMEDIAL WORK
General
This section presents a general plan for correcting the majority of track deficiencies. The plan is
organized as a list of 14 remedial actions, numbered in general work sequence order. The cost estimates
for each remedial action are broken down between Phase 1 (to be done this year) and Phase 2 (to be
done next year). Table D2 shows a cost estimate summary.
Table C-2. Cost Estimate Summary
REMEDIAL ACTION
No.
Description
PHASE 1
PHASE 2
TOTAL
1.
Remove Vegetation
$ 1,200
$ 2,400
$ 3,600
2.
15,000
35,000
50,000
3.
Rail Defect Inspection
5,000
---
5,000
4.
Replace Defective Rail
13,600
13,600
27,200
5.
29,950
33,470
63,420
6.
Tie Replacement
140,000
100,000
240,000
7.
Respace Ties
3,250
8,125
11,375
8.
Tighten Bolts/Spikes
18,700
18,700
37,400
9.
Restore Turnouts
19,800
12,150
31,950
10.
33,580
25,200
58,780
11.
147,640
86,060
233,700
12.
Surface Track
55,200
32,175
87,375
13.
Herbicide Application
3,200
2,600
5,800
14.
On-Site Inspection
12,000
12,000
24,000
Subtotal
$ 498,100
$ 381,500
$ 879,600
10% Contingency
49,810
38,150
87,960
TOTAL
$ 547,910
$ 419,650
$ 967,560
C-22