The amount of lubricants required is computed separately for
each railway division on a monthly basis. These requirements are
based on an estimate of 1,000 pounds per month for each train running
each way per day over each division.
Spare parts requirements are computed by the same method as for
lubricants except that the basis is 1.5 short tons per month for each
train per day in each direction.